Articles → PROJECT MANAGEMENT → Risk Register In Project Management

Risk Register In Project Management






What Is The Risk Register?





Fields In The Risk Register






  1. Risk No
  2. Risk Description (contains - Causes, Events, and Effect)
  3. Severity (Red, Amber, Green)
  4. Owner
  5. Status (Open and close)
  6. Mitigation/contingency plan
  7. Date of risk
  8. Due Date of Risk
  9. Probability of Risk

Sample Risk Register


Column NameData
Risk NoRisk_001
Risk DescriptionCauses – The UX developer is not onboarded

Event - Screens are not designed on time

Effect - Approval will not be given on time
SeverityRed
OwnerKaran
StatusOpen
Mitigation/Contingency PlanBorrow the resource from another team and share the project WBSE
Date of Risk12-Apr-2021
Due Date of Risk21-May-2021
ProbabilityMost Likely



Posted By  -  Karan Gupta
 
Posted On  -  Friday, April 30, 2021