Articles → PROJECT MANAGEMENT → Risk Register In Project Management
Risk Register In Project Management
What Is The Risk Register?
Fields In The Risk Register
- Risk No
- Risk Description (contains - Causes, Events, and Effect)
- Severity (Red, Amber, Green)
- Owner
- Status (Open and close)
- Mitigation/contingency plan
- Date of risk
- Due Date of Risk
- Probability of Risk
Sample Risk Register
| Column Name | Data |
|---|
| Risk No | Risk_001 |
| Risk Description | Causes – The UX developer is not onboarded
Event - Screens are not designed on time
Effect - Approval will not be given on time |
| Severity | Red |
| Owner | Karan |
| Status | Open |
| Mitigation/Contingency Plan | Borrow the resource from another team and share the project WBSE |
| Date of Risk | 12-Apr-2021 |
| Due Date of Risk | 21-May-2021 |
| Probability | Most Likely |
| Posted By - | Karan Gupta |
| |
| Posted On - | Friday, April 30, 2021 |