Burn-Down Chart In Agile
Purpose
- How many story points are left?
- How much time is remaining to complete the pending task?
Burn-Down Chart Explained
- Total effort
- Amount of effort remaining
- Number of days in the sprint
- Number of days remaining
- Ideal trend
- Current trend
| Day 1 | Day 2 | Day 3 | Day 4 | Day 5 |
---|
Story points pending | 80 | 64 | 48 | 32 | 16 |
| Day 1 | Day 2 | Day 3 | Day 4 | Day 5 |
---|
Story points pending | 80 | 60 | 40 | 25 | 16 |